The projected work schedule for the phase 3 water system improvement project in Hamilton, which will run from August through December 2017 with final paving in May 2018. All dates are subject to change

  • Lincoln Avenue: Aug. 14 – Sept. 11, 2017
  • Union Street: Aug. 14 – Sept. 18, 2017
  • Day Avenue: Aug. 30 – Sept. 18, 2017
  • Lorenzo Street: Sept. 8 – Sept. 20, 2017
  • Western Avenue: Sept. 12 – Sept. 28, 2017
  • Willow Street: Sept. 15 – Oct. 12, 2017
  • Roosevelt Avenue: Sept. 22 – Oct. 2, 2017
  • Central Avenue: Sept. 29 – Oct. 11, 2017
  • Cummings Avenue: Oct. 3 – Oct. 20, 2017
  • Moynihan Road: Oct. 3 – Nov. 1, 2017
  • Railroad Avenue: Oct. 5 – Nov. 3, 2017
  • Pleasant Street: Oct. 11 – Nov. 13, 2017
  • Elliot Street: Oct. 13 – Nov. 20, 2017
  • Home Street: Oct. 17 – Dec. 1, 2017
  • Honeysuckle Road: Oct. 18 – Nov. 20, 2017
  • Naples Road: Oct. 23 – Dec. 15, 2017
  • Red Coach Road: Oct. 26 – Dec. 4, 2017
  • Savoy Road: Oct. 26 – Dec. 27, 2017
  • Howard Street: Nov. 1 – Nov. 9, 2017
  • Madonna Drive: Nov. 2 – Dec. 15, 2017
  • Lois Street: Nov. 13 – Nov. 21, 2017
  • Essex Street: Nov. 22 – Dec. 19, 2017
  • Anthony Road: Dec. 8 – Dec. 27, 2017
  • Chebacco Road: Dec. 20, 2017 – Jan. 2, 2018

Final road paving for entire project: May, 7 – May, 25, 2018